1952 The replacement station opened; this was the first London power station designed to be fired exclusively with pulverised coal. The station was equipped with three [[English Electric Co]] 30 MW turbine-alternators generating at 11 kV. Steam was supplied by three coal-fired [[Babcock and Wilcox]] boilers, with condenser cooling water taken from the river. Steam pressure and temperature at the turbine stop valves was 600 psi (41.4 bar) and 454°C. The first TA was commissioned in the summer of 1951, subsequent sets coming into use by the spring of 1952. <ref>[http://en.wikipedia.org/wiki/Blackwall_Point_Power_Station] Wikipedia</ref> | 1952 The replacement station opened; this was the first London power station designed to be fired exclusively with pulverised coal. The station was equipped with three [[English Electric Co]] 30 MW turbine-alternators generating at 11 kV. Steam was supplied by three coal-fired [[Babcock and Wilcox]] boilers, with condenser cooling water taken from the river. Steam pressure and temperature at the turbine stop valves was 600 psi (41.4 bar) and 454°C. The first TA was commissioned in the summer of 1951, subsequent sets coming into use by the spring of 1952. <ref>[http://en.wikipedia.org/wiki/Blackwall_Point_Power_Station] Wikipedia</ref> | ||
==See Also== | ==See Also== | ||
Line 23: | Line 22: | ||
{{DEFAULTSORT: }} | {{DEFAULTSORT: }} | ||
[[Category: Town - Greenwich]] | [[Category: Town - Greenwich]] | ||
[[Category: Electricity | [[Category: Electricity Power Stations]] |
Latest revision as of 09:52, 28 March 2025


1900 Power station built by Blackheath and Greenwich Electric Light Co on the Greenwich Peninsula, on the site of the East Greenwich tide mill.
At some point became part of the South Metropolitan Electric Light and Power Co
1927 Selected for temporary arrangement under the South-East England Electricity Scheme[1]
1947 The station closed; final capacity 15 MW.
1948 South Metropolitan was reconstructing the Blackwall Point Power Station to produce 90MW[2].
1952 The replacement station opened; this was the first London power station designed to be fired exclusively with pulverised coal. The station was equipped with three English Electric Co 30 MW turbine-alternators generating at 11 kV. Steam was supplied by three coal-fired Babcock and Wilcox boilers, with condenser cooling water taken from the river. Steam pressure and temperature at the turbine stop valves was 600 psi (41.4 bar) and 454°C. The first TA was commissioned in the summer of 1951, subsequent sets coming into use by the spring of 1952. [3]
See Also
Sources of Information
- Wikipedia [2]