Blackburn, Burnley, Accrington and Colne Railway: Difference between revisions
Created page with "The railway was authorised in 1845, and under the same Act its amalgamation with the East Lancashire Railway was authorised. It was opened thus: *Blackburn - Accrington,..." |
No edit summary |
||
Line 5: | Line 5: | ||
*Burnley-Colne, February 1st, 1849; | *Burnley-Colne, February 1st, 1849; | ||
The line from the [[East Lancashire Railway]] at Stubbins Junction to Arcrington was opened on August 17th, 1848. The [[Blackburn Railway]] was an independent concern, and was opened from Bolton to Blackburn on August 12th 1848, and from Blackburn to Chatburn on June 22nd, 1850. <ref>The Engineer 1924/11/07</ref> | The line from the [[East Lancashire Railway]] at Stubbins Junction to Arcrington was opened on August 17th, 1848. | ||
The [[Blackburn Railway]] was an independent concern, and was opened from Bolton to Blackburn on August 12th 1848, and from Blackburn to Chatburn on June 22nd, 1850. <ref>[[The Engineer 1924/11/07]]</ref> | |||
==See Also== | ==See Also== | ||
Line 14: | Line 16: | ||
{{DEFAULTSORT:}} | {{DEFAULTSORT:}} | ||
[[Category: | [[Category: Railway Companies]] |
Latest revision as of 06:20, 20 April 2015
The railway was authorised in 1845, and under the same Act its amalgamation with the East Lancashire Railway was authorised. It was opened thus:
- Blackburn - Accrington, June 19th, 1848;
- Accrington- Burnley, September 18th, 1848;
- Burnley-Colne, February 1st, 1849;
The line from the East Lancashire Railway at Stubbins Junction to Arcrington was opened on August 17th, 1848.
The Blackburn Railway was an independent concern, and was opened from Bolton to Blackburn on August 12th 1848, and from Blackburn to Chatburn on June 22nd, 1850. [1]