Grace's Guide To British Industrial History

Registered UK Charity (No. 115342)

Grace's Guide is the leading source of historical information on industry and manufacturing in Britain. This web publication contains 162,258 pages of information and 244,499 images on early companies, their products and the people who designed and built them.

Grace's Guide is the leading source of historical information on industry and manufacturing in Britain. This web publication contains 147,919 pages of information and 233,587 images on early companies, their products and the people who designed and built them.

Chirk Aqueduct

From Graces Guide
Revision as of 13:54, 19 March 2022 by JohnD (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Aqueduct in foreground and Chirk Viaduct behind
Im1960BW1-ChirkAq.jpg
JD Chirk Aqueduct02.jpg
JD Chirk Aqueduct01.jpg

Chirk Aqueduct is a 70-foot high and 710-foot long navigable aqueduct that carries what is now the Llangollen Canal across the Ceiriog Valley near Chirk, on the England-Wales border.

The aqueduct followed Telford's innovative Longdon-on-Tern Aqueduct on the Shrewsbury Canal, and was a forerunner of the Pontcysyllte Aqueduct, also on the Llangollen Canal. Telford was a pioneer in the use of cast iron in bridges as well as aqueducts.

The aqueduct has ten arches, each with a span of 40 feet (12 m). The canal water level is 65 feet (20 m) above the ground and 70 feet (21 m) above the River Ceiriog. The first stone was laid on 17 June 1796.

The aqueduct was designed by Thomas Telford and William Jessop for the Ellesmere Canal, and completed in 1801.

It now possesses a cast iron trough, effectively hidden by the masonry walls. However, as originally built, the trough only had cast iron plates for the base.

A contemporary drawing[1] of a section through the aqueduct shows some interesting features. In the upper part of the masonry are four narrow longitudinal chambers. The central wall divding the inner pair of chambers serves to support the iron floor plates of the trough to prevent bending. The plates are flanged at each end so that they can be bolted to each other. There are no flanges shown at the sides, but there are holes for vertical bolts. Now things become less clear. There are are a number of components within the structure which we will assume to be cast iron. These include three layers of what may be 'grid-irons' located near the top, bottom and mid height of the piers. These are horizontal transverse bars, notched on the upper surface, with a number of longitudinal bars locating in the notches. A short distance above the springing of the arches is a series of six bars. Further up is shown a horizontal bar, presumably a tie-bar, passing through the four voids in the arched portion, and engaging with a pair of transverse bars in the outer wall. Further up, just below the bottom of the trough, there is a thick plate on each side, outboard of which is a transverse bar. The floor plates would have been bolted to this. On top of the thick plates sit ashlar blocks which form the sides of the channel. Outboard of these, and also sitting on the plate, are walls of 'hard-burnt bricks' sealed with 'Parker's Cement'.

The arrangement offered considerable weight-saving, as well as the prospect of freedom from the problems of water leakage into the masonry which plagued other aqueducts. William Hazledine provided the iron plates.

In fact leakage proved to be a problem, and in December 1868 the Chief Engineer, John Beech, recommended the addition of cast iron side plates to form a trough. A contract was placed with Cochrane, Grove and Co, who decided that the optimum solution would be to discard the original base plates and provide an all new trough made of flanged cast iron plates bolted together. Each 'pitch' comprised a left and right hand side plate and a pair of bottom plates. Photo here. The 'modular' construction allowed the work to be completed with the minimum of downtime. Work started on 20 September 1869 and was completed on 25th.

For many years the aqueduct has served for supplying water as well as for boating use.

The Chirk Tunnel starts at the north end of the Chirk Aqueduct, allowing the canal to continue on towards Llangollen.


See Also

Loading...

Sources of Information

  1. In Thomas Telford's 'Atlas'
  • 'Thomas Telford's Aqueducts on the Shropshire Union Canal' by Ron Quenby, Swan Hill Press, 1992